After receiving a phone call about potentially delivering the Medical Gas requirements for several Nightingale Hospitals across the country, the instruction was received first by the North East team. We set to work over a weekend to design the required Oxygen, Medical Air and Vacuum Medical Gas Systems with a view to starting installation works on site on Monday.

The project provided 330 general ward beds and a further 130 ICU bed spaces.

We provided 2 x Oxygen, 1 x Medical Air 4 and 1 x Vacuum Terminal Unit at each of the 460 bed spaces, totalling nearly 2,000 terminal units. It was an amazing effort by all trades on site to complete the installation in under 4 weeks with site working 24 hours a day, 7 days a week.

We also provided a new Triplex Vacuum Plant and Quadruplex Medical Air Plant along with all the Medical Terminal Units, Valves and Alarms as required for the project.

This was a monumental effort by everyone involved in the project, all working together to one common goal and something we were extremely proud to be a part of. Delivery of this project in under 4 weeks could not have been possible without the support of our staff and supply chain.